Mammoet transports LPG bullets to Sunrise Energy’s Saldanha LPG terminal

Mammoet transports LPG bullets to Sunrise Energy’s Saldanha LPG terminal

July 30, 2016: Mammoet transported and installed five LPG pressure vessels (bullets), the largest of their kind in Africa and the Southern Hemisphere.

They weighed 584 metric tonnes each and were transported 2.7 kilometres from Efficient Engineering’s fabrication workshops to the Sunrise Energy site in Saldanha, Western Cape, South Africa.

South Africa is currently experiencing a shortage of liquid petroleum gas (LPG) and demand is increasing. To meet the country’s needs, Sunrise Energy is in the process of constructing a LPG Import Terminal in Saldanha. It will be used to import and distribute commercial LPG (a combination of propane and butane gas) to households, commercial organisations and small industrial businesses.

The terminal is scheduled for commission in April 2017.

Mammoet was contracted by Efficient Engineering for the transportation and installation of the LPG bullets from the fabrication workshop to the Sunrise Energy site.

The transport involved two prime movers and two 10 Axle Kamag 4 file trailer configurations with 300-tonne Kamag turntables on each configuration and a Goldhofer SPT pushing at the rear.

The mostly off-road route included crossing a railway within a ten minute window, coordinated with the operators of the busy line, and the addition of an extra truck to provide power to ascend a steep gravel road with an 8 degree incline.

Once onsite, a carefully planned and synchronised manoeuver enabled Mammoet to rotate the trailers underneath their load enabling the bullet, now perpendicular to its trailers, to be driven up two temporary inclines towards the foundation. This tricky trailer rotation maneuver saved vital installation time as it meant the bullet was in position to ascend the ramp in just one hour.

The alternative method, involving removing then replacing each bullet on the trailers after aligning the trailers with the ramps, would have taken a day for each bullet.

Having ascended to the installation area, each bullet was jacked down and skidded to their final position where they were set onto purpose-built sand cradles.

By installing the bullets using skidding equipment, rather than directly from the trailers, Efficient Engineering’s client Sunrise Energy could reduce the amount of civil works they had to carry out on site.

The project was complete by June 3, 2016, within the project’s tight 25 day installation schedule.

Related Posts

Implementation of Lomé Declaration will drive Africa’s air cargo growth: ICAO Council President

Implementation of Lomé Declar ...

Jun 28, 2017: Air cargo segment’s growth depends on technological innovation, regulatory reforms and investment in infrastru ...

Boeing and Royal Air Maroc signs agreement to convert passenger plane into freighter

Boeing and Royal Air Maroc sig ...

Jun 28, 2017: Moroccan Company Royal Air Maroc has entered into an agreement with aircraft manufacturer Boeing for conversion of B ...

Spice jet ropes in TCI to manufacture Galleys for B737 Max aircraft

Spice jet ropes in TCI to manu ...

Jun 28, 2017: TCI, a global player in the aviation industry in design, certification and manufacturing of cabin interiors, has com ...

Vertical integration and innovations vital to improve cold chain for perishables moved by air

Vertical integration and innov ...

Jun 28, 2017: Tracking the transportation process of perishable commodities from the time it leaves the manufacturer to the time i ...